Centronium Phase 1 set out to launch the chain safely and prove decentralization through public block data — not slogans. This is the launch plan, and the chain's answer to it, side by side.
A new chain that launches without foundation support stalls. A chain that launches with permanent foundation support is centralized in everything but name. Phase 1 was designed to thread the needle — and produce auditable evidence that it did.
Launch the chain safely, validate live PoUW API consensus, and begin the transition from foundation-operated mining to independent miner production.
Show decentralization through public block data, not claims.
— From Launch Plan §01
Chain launched Feb 26. PoUW consensus validated under live load. Foundation mining reduced through four measured handoff windows.
By Apr 10, the network produced 1,140–1,190 blocks/day without active foundation support — within 18% of the 1,440-block target.
The strategy called for foundation-supported launch, then a deliberate baseline test, then progressive handoff windows, then standby reserve. Each transition was intentional — and visible in daily block counts.
Foundation mining ran continuously to protect early production while independent miners onboarded.
Foundation support pulled. Goal: measure what independent miners could produce alone — knowing the result might be near zero.
Recurring reduction windows let independent miners take more load. Each dip shallower than the last — the curve the plan predicted.
Independent production locked in. Foundation miners moved to emergency reserve. Daily output stable across 23+ consecutive days.
Daily block production across all 67 days. The dips are not failures — they are the handoff windows specified in §5 of the launch plan. The recoveries are the independent miner network finding its footing.
67 DAYS · TARGET 1,440/DAY · ALL DATA FROM CENTROSCAN
The launch plan defined ten criteria for Phase 1 completion. Each is checked against publicly verifiable data from CentroScan.
All 67 days of Phase 1, newest first. Peak day, baseline test, and handoff windows tagged inline.
| Date | Day | Blocks Mined | New CENTRO |
|---|
Centronium Phase 1 has completed its controlled decentralization handoff. The network launched with foundation support, measured independent mining capacity through a documented baseline test, progressively reduced foundation dependence across four handoff windows, and reached stable production through independent miners.
Foundation miners have moved to standby reserve. Phase 2 Growth is now active.